Revit 2015
In the door schedule creation menu there is a field available to add "phase created" to the door schedule, but the same field does not appear in the room schedule creation menu. Is there a way to make that field available to the room schedule as well?
|
This user is offline |
|
|
|
site moderator|||
Joined: Tue, May 16, 2006
13079 Posts
|
Look in your schedule properties, the phase setting is there.
|
This user is offline |
|
|
active
Joined: Thu, Sep 9, 2010
105 Posts No Rating |
The phase that shows in properties just sorts ... I don't want to sort them, I want to add a column in my schedule.
|
This user is offline |
|
|
site moderator|||
Joined: Tue, May 16, 2006
13079 Posts
|
Oh, I miss understood your question. You can't do this with rooms in one schedule. You can have a seperate schedule for what rooms are in each phase.
|
This user is offline |
|
|
active
Joined: Thu, Sep 9, 2010
105 Posts No Rating |
Can I add my own shared parameter and sort of fake it into working?
|
This user is offline |
|
|
active
Joined: Mon, Aug 4, 2008
153 Posts
|
Try followings:
1. Go to your Room Schedule, in "Properties", click "Fields", then the "Schedule Properties" window will be shown.
2. Click "Add Parameter", then the "Parameter Properties" window will be shown, in "Group parameter under:" botton, use pull-down list select "Phasing", in "Type of Parameter", pull down list select "Text" (try this for the time being, you can modify it later). Give a name such as "Project Phasing". Now you have the "Project Phasing" column in you schedule.
3. In your Schedule Properties, now you have "Phasing", you can select "New Construction" or "Existing"
|
This user is offline |
|
|
active
Joined: Thu, Sep 9, 2010
105 Posts No Rating |
Yes, Thanks. That was what I talked about "sort of faking it". It is now a double entry for room phasing but it does add a column to the schedule. Thanks. If anyone knows a better way please let me know.
|
This user is offline |
|
|
|
Similar Threads |
Adding Room Names to Door Schedule |
Community >> Newbies
|
Sun, Aug 21, 2016 at 11:03:06 AM
|
7
|
adding room number to window schedule |
Revit Building >> Technical Support
|
Wed, Oct 15, 2014 at 11:05:05 AM
|
4
|
Room Numbering & Phases |
Revit Building >> Technical Support
|
Thu, Aug 27, 2015 at 3:01:49 AM
|
2
|
Can't filter "Phase Created" in MTO for linked Revit files? |
Revit Building >> Technical Support
|
Mon, May 12, 2014 at 7:01:45 AM
|
2
|
Room finish Schedule showing Deleted Rooms |
Revit Building >> Technical Support
|
Wed, Aug 26, 2009 at 3:56:37 PM
|
1
|
|
|
Site Stats
Members: | 1991303 | Objects: | 22879 | Forum Posts: | 152184 | Job Listings: | 3 |
|