Forums >> Revit Building >> Technical Support >> Typical Bathroom in Multiple Phase Project
|
|
|
active
Joined: Mon, Oct 25, 2010
6 Posts No Rating |
I've searched for an answer to this problem and haven't found anything. If this is a repeat, please accept my apologies.
Project: Hospital ward, built in 8 phases. Working drawings will be issued 1) as a full set for bidding, and 2) as a single phase for construction.
We want to note & detail one bathroom and reference it in 7 of the phases, so it would appear on 7 different sheets.
Is there a straightforward solution?
Thanks,
Julie
|
This user is offline |
|
 | |
|
|
active
Joined: Mon, Oct 25, 2010
6 Posts No Rating |
Using Revit Architecture, 2014
|
This user is offline |
|
 |
|
site moderator|||
Joined: Tue, May 16, 2006
19889 Posts
 |
I assume you are you asking about the callouts? .... or are you talking about using the same view on seven sheets?
Obviously you can duplicate a view with detailing as a dependent and place the duplicated views on multiple sheets. I would assume you can then use the reference other view to call those out but the phase of the callout may cause problems.
Please let us know when you test it out.
|
This user is offline |
|
 |
|
active
Joined: Mon, Oct 25, 2010
6 Posts No Rating |
It worked! I didn't think of this approach - I haven't spent a lot of time working with dependent views. There are no apparent problems with the phase difference.
Thanks for the help.
|
This user is offline |
|
 |
 |
Similar Threads |
|
Hosting Revit Building Pads Error |
Revit Building >> Technical Support
|
Tue, Apr 7, 2009 at 4:56:12 PM
|
1
|
|
Maintaining "Phase Demolished" properties. |
Revit Structure >> Technical Support
|
Thu, Jun 18, 2015 at 8:19:39 AM
|
2
|
|
Phase filtering |
Revit Building >> Technical Support
|
Wed, Nov 22, 2006 at 9:19:32 PM
|
1
|
|
Objects showing in wrong plan view |
Revit Building >> Technical Support
|
Sun, Oct 10, 2021 at 8:10:49 AM
|
1
|
|
Phasing: creating 3 phases, filter out middle |
Revit Building >> Technical Support
|
Thu, Jan 22, 2015 at 9:02:29 AM
|
1
|
 |
|
Site Stats
Members: | 2167229 | Objects: | 23399 | Forum Posts: | 152368 | Job Listings: | 0 |
|