Fri, Dec 2, 2011 at 1:49:06 PM | Coordination Review - Actions not displaying

#1

sapsych


active

Joined: Wed, Nov 2, 2011
4 Posts
No Rating


I have an REVIT ARCH model with ceilings and light fixtures.  I am working in REVIT MEP and have copy/monitored the light fixtures into my model.  When I change the location of the fixtures in the ARCH model, and then open up the MEP model, the program informs me of the need for Coordination Review.  When I perform the review, it shows the different locations of the fixture, but only gives me three options for ACTION. postpone, reject, or accept the difference.  According to the HELP - Users guide, I should have modify, rename, move, Ignore new elements, etc.  But the coordination review window does not list these additional actions.  Also, if I would select move, would the program automatically relocate the fixture to the new location in my MEP model??  Is this how it is supposed to work??  What is causing the issue?? How do I correct this situation??

Thanks,


This user is offline

 

Sat, Dec 3, 2011 at 8:56:11 AM | Coordination Review - Actions not displaying

#2

WWHub


site moderator|||

Joined: Tue, May 16, 2006
13079 Posts
3.5 Stars: 389 Votes


I guess I will have to look at what the help says when I get back in Monday.  I have only known the 3 options you listed.

 

You can always modify, rename - move these items and it is not part of the review process.  If you do move these items, it will not move them in the linked model but will set up a "needs coordination review" for the link.


This user is offline

 

Sat, Dec 3, 2011 at 12:59:52 PM | Coordination Review - Actions not displaying

#3

sapsych


active

Joined: Wed, Nov 2, 2011
4 Posts
No Rating


Thanks for the reply.

Enclosed is the list of Actions that I found in the help section.

It states that not all actions will be listed, so I do not know the conditions for each action in order to be made available for use.  I can manually move the fixture to the revised location, but it seems like the program has the capability to do this automatically.



This user is offline

 

Sun, Dec 4, 2011 at 8:16:10 AM | Coordination Review - Actions not displaying

#4

WWHub


site moderator|||

Joined: Tue, May 16, 2006
13079 Posts
3.5 Stars: 389 Votes


What I believe you might be refering to is "to accept" a change.  And yes, if you accept a change made in a linked model, to an item you have copy-monitored, then that item will be changed in your model.  But that was noy what you asked. 

 

If you reject a change, then that will be noted and the other party will be told when they do their next coordination review.  If you postpone ... the item remains on your "action-list".  But no real "automatic" action takes place - there is an approval process.


This user is offline

 

Mon, Dec 5, 2011 at 9:56:32 AM | Coordination Review - Actions not displaying

#5

sapsych


active

Joined: Wed, Nov 2, 2011
4 Posts
No Rating


Thanks for the reply.

I understand the "Accept" choice and, now that you have explained it, I understand the "Reject" choice. Also, the "Postpone" option.  Listed in the additional options, from the Help section and included in this posting, is the "Move" choice for Actions.  This is explained and seems to be the automatic version of moving the object to the new location that is being monitored. 

Move: A monitored element has moved. Select Move to apply this change to the corresponding element in the current project.

There are other options as well, just don't know why they do not show up in the Actions drop down menu.

It seems that if I "Accept" that I have to move the object manually, and my understanding is that it will continue to be monitored.

Thanks,

 


This user is offline

 

Search this ThreadSearch this Thread | Page 1 of 1 |



Similar Threads

Thread/Thread Starter

Forum

Last Post

Replies

Coordination review issue

Community >> Newbies

Thu, Mar 17, 2011 at 2:35:20 PM

3

Coordination review with wall openings

Revit Structure >> Technical Support

Tue, Sep 18, 2007 at 8:57:20 AM

0

Copy monitor/coordination review - some elements missing & some not moved

Revit Structure >> Technical Support

Wed, Jun 24, 2009 at 5:20:19 PM

0

copy/monitor driving me crazy

Revit Structure >> Technical Support

Thu, Dec 15, 2011 at 1:06:41 PM

0

BIM coordination role

General Discussion >> Revit Project Management

Tue, Apr 9, 2013 at 4:58:33 PM

5

Site Stats

Members:

1990159

Objects:

22877

Forum Posts:

152180

Job Listings:

3

Sponsored Ads

Home | Forums | Downloads | Gallery | News & Articles | Resources | Jobs | Search | Advertise | About RevitCity.com | Link To Us | Site Map | Member List | Firm List | Contact Us

Copyright 2003-2010 Pierced Media LC, a design company. All Rights Reserved.

Page generation time: 1.3716

Login

User Name:

Password:

Remember Me  

Forgot Password?

Search Forums

Advanced Search

Search Forums

Advanced Search


Clear Highlights


Clear Highlights